Activities
Working Groups will be formed to deliver outputs per objective
OBJECTIVE 1:
To have a detailed appreciation of Korogocho
Outputs
- General socio-economic study for Korogocho
- Maps for Korogocho
- Situation analysis of Korogocho
Actors: Provincial administration, Community, CBOs, FBOs, MoL, MoH, CCN, UN-Habitat and MoLG
Lead Agency: MOLG and UN-Habitat
Activities under output 1:
- Define the structure of the study
- Conduct interviews, hold meetings, and group discussions
Activities under output 2:
- Mapping of existing physical situation
Activities under output 3:
- Sensitize Community
- Carry out an enumeration of residents
- Conduct socio-economic analysis
Methodology:
- Set up a Working Group under the chairmanship of UN Habitat and MoLG.
- The working group to draw up a work plan with budget, financial plan and time frame.
- The work plan to be presented before the Steering Committee for approval.
- Implement approved work plan.
- Money will be released periodically in response to specific requests made by the working group as approved by the steering committee.
OBJECTIVE 2:
To prepare an Advisory Physical Plan for Korogocho
Output:
- Advisory Physical Plan
Actors: CCN, Community, MoLG and MoL
Lead Agency: MoL
Activities under output:
- Field reconnaissance
- Hold stakeholder meetings
- Drawing of plan
Methodology:
- Set up Working Group under the chairmanship of Ministry of Lands.
- The working group to draw up a work plan with budget, financial plan and time frame.
- The work plan to be presented before the Steering Committee for approval.
- Implement work plan.
- Money will be released periodically in response to specific requests made by the working group as approved by the steering committee.
OBJECTIVE 3:
To build capacity of various actors/Institutions
Outputs:
- Capacity needs assessment
- Capacity building plan
- Implemented capacity building plan
- Korogocho residents are informed on slum upgrading approaches in Kenya
Actors: MoH, NGOs, MoLG, UN-Habitat, CCN, MoL, MoF and Training institutions
Lead Agency: UN-Habitat and MoLG
Activities under output 1:
- Conduct capacity needs assessment consultatively
Activities under output 2:
- Prepare capacity building plan
Activities under output 3:
- Conduct capacity building sessions
Activities under output 4:
- Workshops to prepare and disseminate slum upgrading experiences in Kenya
Methodology:
- Set up Working Group under the chairmanship of UN-Habitat and MoLG.
- The working group to draw up a work plan with budget, financial plan and time frame.
- The work plan to be presented before the Steering Committee for approval.
- Implement work plan.
- Money will be released periodically in response to specific requests made by the working group as approved by the steering committee.
OBJECTIVE 4:
To prepare a Sustainable Integrated Plan for upgrading Korogocho
Outputs:
- Consensus on services and improvements
- Layout designs
- Financing plan
- Action plan
Actors: CCN, MoLG, MoL, MoF, MoH and UN-Habitat
Lead Agency: UN-Habitat
Activities under output 1:
Activities under output 2:
- Prepare layout designs and services
- Obtain consensus through meetings
Activities under output 3:
- Develop costing for the works and time frame
- Convene a developers consultation forum
Activities under output 4:
- Discuss plan
- Finalize plan
Methodology:
- Set up Working Group under the chairmanship of UN Habitat
- The working group to draw up a work plan with budget, financial plan and time frame.
- The work plan to be presented before the Steering Committee for approval.
- Implement work plan.
- Money will be released periodically in response to specific requests made by the working group as approved by the steering committee.
OBJECTIVE 5:
To provide collective security of tenure to the residents of Korogocho
Output:
- Alternative land tenure system(s)
Actors: CCN, MoLG, MoL, MoH, Community and UN-Habitat
Lead Agency: MoL
Activities under output:
- Workshop(s) on alternative land tenure systems
- Submission of agreed land tenure system for scrutiny and approval by CCN and CoL
Methodology:
- Set up a Working Group under the chairmanship of the MoL.
- The working group to draw up a work plan with budget, financial plan and time frame.
- The work plan to be presented before the Steering Committee for approval.
- Implement work plan.
- Money will be released periodically in response to specific requests made by the working group as approved by the steering committee.
OBJECTIVE 6:
To implement concrete improvement to assure visible impact
Output:
Actors: PMU, Steering Committee, CCN, UN-Habitat, Project team, MoLG, Contractors, MoL and MoH
Lead Agency: CCN
Activities under output:
- Prepare project delivery schedule
- Prepare tender documents
- Evaluation of and award of tenders
- Supervision of projects
- Completion and handing over
Methodology:
- Set up Working Group under the chairmanship City Council of Nairobi.
- The working group to draw up a work plan with budget, financial plan and time frame.
- The work plan to be presented before the Steering Committee for approval.
- Implement work plan.
- Money will be released periodically in response to specific requests made by the working group as approved by the steering committee.